Bill Ballou 2cd54118a1 docs: add implementation task list with 67 tasks
Task breakdown by user story:
- US1 Load XER File (P1): 17 tasks
- US2 Query Activities (P1): 10 tasks
- US3 Query Relationships (P2): 9 tasks
- US4 Query Summary (P3): 9 tasks

TDD mandated: test tasks precede implementation tasks.
Parallel opportunities identified for models, table handlers,
and concurrent user story development after US1.
2026-01-06 21:02:52 -05:00

12 KiB

Tasks: Project Schedule Tools

Input: Design documents from /specs/001-schedule-tools/ Prerequisites: plan.md, spec.md, research.md, data-model.md, contracts/

Tests: TDD is mandated by constitution - tests MUST be written and fail before implementation.

Organization: Tasks are grouped by user story to enable independent implementation and testing.

Format: [ID] [P?] [Story] Description

  • [P]: Can run in parallel (different files, no dependencies)
  • [Story]: Which user story this task belongs to (US1, US2, US3, US4)
  • Include exact file paths in descriptions

Path Conventions

  • Source: src/xer_mcp/
  • Tests: tests/
  • Config: pyproject.toml

Phase 1: Setup (Shared Infrastructure)

Purpose: Project initialization and basic structure

  • T001 Create project directory structure per plan.md in src/xer_mcp/
  • T002 Initialize Python project with uv and create pyproject.toml with dependencies (mcp, pytest, pytest-asyncio, ruff)
  • T003 [P] Configure ruff for linting and formatting in pyproject.toml
  • T004 [P] Create src/xer_mcp/init.py with version 0.1.0
  • T005 [P] Create tests/conftest.py with sample XER file fixtures

Phase 2: Foundational (Blocking Prerequisites)

Purpose: Core infrastructure that MUST be complete before ANY user story can be implemented

⚠️ CRITICAL: No user story work can begin until this phase is complete

  • T006 Create data models in src/xer_mcp/models/init.py (export all models)
  • T007 [P] Create Project dataclass in src/xer_mcp/models/project.py
  • T008 [P] Create Activity dataclass in src/xer_mcp/models/activity.py
  • T009 [P] Create Relationship dataclass in src/xer_mcp/models/relationship.py
  • T010 [P] Create PaginationMetadata dataclass in src/xer_mcp/models/pagination.py
  • T011 Create SQLite schema in src/xer_mcp/db/schema.py with all tables and indexes
  • T012 Create database connection manager in src/xer_mcp/db/init.py
  • T013 Create MCP server skeleton in src/xer_mcp/server.py with stdio transport
  • T014 Create base table handler abstract class in src/xer_mcp/parser/table_handlers/base.py
  • T015 Create error types and NO_FILE_LOADED error in src/xer_mcp/errors.py

Checkpoint: Foundation ready - user story implementation can now begin


Phase 3: User Story 1 - Load XER File (Priority: P1) 🎯 MVP

Goal: Parse XER files and load schedule data into SQLite database

Independent Test: Load a sample XER file and verify projects, activities, relationships are stored in SQLite

Tests for User Story 1

NOTE: Write these tests FIRST, ensure they FAIL before implementation

  • T016 [P] [US1] Contract test for load_xer tool in tests/contract/test_load_xer.py
  • T017 [P] [US1] Integration test for XER parsing in tests/integration/test_xer_parsing.py
  • T018 [P] [US1] Integration test for multi-project handling in tests/integration/test_multi_project.py
  • T019 [P] [US1] Unit test for XER parser in tests/unit/test_parser.py
  • T020 [P] [US1] Unit test for table handlers in tests/unit/test_table_handlers.py

Implementation for User Story 1

  • T021 [US1] Create XER parser main class in src/xer_mcp/parser/xer_parser.py
  • T022 [P] [US1] Create PROJECT table handler in src/xer_mcp/parser/table_handlers/project.py
  • T023 [P] [US1] Create TASK table handler in src/xer_mcp/parser/table_handlers/task.py
  • T024 [P] [US1] Create TASKPRED table handler in src/xer_mcp/parser/table_handlers/taskpred.py
  • T025 [P] [US1] Create PROJWBS table handler in src/xer_mcp/parser/table_handlers/projwbs.py
  • T026 [P] [US1] Create CALENDAR table handler in src/xer_mcp/parser/table_handlers/calendar.py
  • T027 [US1] Create table handler registry in src/xer_mcp/parser/table_handlers/init.py
  • T028 [US1] Create database loader in src/xer_mcp/db/loader.py to insert parsed data into SQLite
  • T029 [US1] Implement load_xer MCP tool in src/xer_mcp/tools/load_xer.py
  • T030 [US1] Register load_xer tool in src/xer_mcp/server.py
  • T031 [US1] Add file-not-found and parse-error handling in src/xer_mcp/tools/load_xer.py
  • T032 [US1] Add multi-project detection and selection logic in src/xer_mcp/tools/load_xer.py

Checkpoint: User Story 1 complete - XER files can be loaded and parsed


Phase 4: User Story 2 - Query Project Activities (Priority: P1)

Goal: List and filter activities, get activity details with pagination

Independent Test: Load XER file, query activities with filters, verify pagination metadata

Tests for User Story 2

NOTE: Write these tests FIRST, ensure they FAIL before implementation

  • T033 [P] [US2] Contract test for list_activities tool in tests/contract/test_list_activities.py
  • T034 [P] [US2] Contract test for get_activity tool in tests/contract/test_get_activity.py
  • T035 [P] [US2] Unit test for activity queries in tests/unit/test_db_queries.py

Implementation for User Story 2

  • T036 [US2] Create activity query functions with pagination in src/xer_mcp/db/queries.py
  • T037 [US2] Implement list_activities MCP tool in src/xer_mcp/tools/list_activities.py
  • T038 [US2] Implement get_activity MCP tool in src/xer_mcp/tools/get_activity.py
  • T039 [US2] Register list_activities and get_activity tools in src/xer_mcp/server.py
  • T040 [US2] Add NO_FILE_LOADED error check to activity tools in src/xer_mcp/tools/list_activities.py
  • T041 [US2] Add date range filtering to list_activities in src/xer_mcp/tools/list_activities.py
  • T042 [US2] Add WBS and activity_type filtering to list_activities in src/xer_mcp/tools/list_activities.py

Checkpoint: User Stories 1 AND 2 complete - activities are queryable


Phase 5: User Story 3 - Query Activity Relationships (Priority: P2)

Goal: Query predecessors, successors, and full relationship network

Independent Test: Load XER file, query relationships for an activity, verify types and lags

Tests for User Story 3

NOTE: Write these tests FIRST, ensure they FAIL before implementation

  • T043 [P] [US3] Contract test for list_relationships tool in tests/contract/test_list_relationships.py
  • T044 [P] [US3] Contract test for get_predecessors tool in tests/contract/test_get_predecessors.py
  • T045 [P] [US3] Contract test for get_successors tool in tests/contract/test_get_successors.py

Implementation for User Story 3

  • T046 [US3] Create relationship query functions in src/xer_mcp/db/queries.py
  • T047 [US3] Implement list_relationships MCP tool in src/xer_mcp/tools/list_relationships.py
  • T048 [US3] Implement get_predecessors MCP tool in src/xer_mcp/tools/get_predecessors.py
  • T049 [US3] Implement get_successors MCP tool in src/xer_mcp/tools/get_successors.py
  • T050 [US3] Register relationship tools in src/xer_mcp/server.py
  • T051 [US3] Add NO_FILE_LOADED error check to relationship tools

Checkpoint: User Stories 1, 2, AND 3 complete - relationships are queryable


Phase 6: User Story 4 - Query Project Summary (Priority: P3)

Goal: Get project overview, milestones, and critical path activities

Independent Test: Load XER file, get summary, list milestones, get critical path

Tests for User Story 4

NOTE: Write these tests FIRST, ensure they FAIL before implementation

  • T052 [P] [US4] Contract test for get_project_summary tool in tests/contract/test_get_project_summary.py
  • T053 [P] [US4] Contract test for list_milestones tool in tests/contract/test_list_milestones.py
  • T054 [P] [US4] Contract test for get_critical_path tool in tests/contract/test_get_critical_path.py

Implementation for User Story 4

  • T055 [US4] Create summary query functions in src/xer_mcp/db/queries.py
  • T056 [US4] Implement get_project_summary MCP tool in src/xer_mcp/tools/get_project_summary.py
  • T057 [US4] Implement list_milestones MCP tool in src/xer_mcp/tools/list_milestones.py
  • T058 [US4] Implement get_critical_path MCP tool in src/xer_mcp/tools/get_critical_path.py
  • T059 [US4] Register summary tools in src/xer_mcp/server.py
  • T060 [US4] Add NO_FILE_LOADED error check to summary tools

Checkpoint: All user stories complete - full MCP server functional


Phase 7: Polish & Cross-Cutting Concerns

Purpose: Improvements that affect multiple user stories

  • T061 [P] Integration test for edge cases in tests/integration/test_edge_cases.py
  • T062 [P] Unit test for models in tests/unit/test_models.py
  • T063 Add logging throughout src/xer_mcp/ modules
  • T064 Run quickstart.md validation - test all documented examples
  • T065 Add main.py entry point in src/xer_mcp/main.py
  • T066 Final type checking with mypy and fix any issues
  • T067 Run ruff format and fix any linting issues

Dependencies & Execution Order

Phase Dependencies

  • Setup (Phase 1): No dependencies - can start immediately
  • Foundational (Phase 2): Depends on Setup completion - BLOCKS all user stories
  • User Story 1 (Phase 3): Depends on Foundational - BLOCKS US2, US3, US4 (they need load_xer)
  • User Story 2 (Phase 4): Depends on US1 (needs loaded data to query)
  • User Story 3 (Phase 5): Depends on US1 (needs loaded data to query)
  • User Story 4 (Phase 6): Depends on US1 (needs loaded data to query)
  • Polish (Phase 7): Depends on all user stories being complete

User Story Dependencies

  • US1 (Load XER): Foundation for all others - MUST complete first
  • US2 (Activities): Can start after US1 - independent of US3, US4
  • US3 (Relationships): Can start after US1 - independent of US2, US4
  • US4 (Summary): Can start after US1 - independent of US2, US3

Within Each User Story

  • Tests MUST be written and FAIL before implementation
  • Models before services/queries
  • Queries before MCP tools
  • Core implementation before error handling
  • Register tools in server.py after implementation

Parallel Opportunities

Phase 2 (Foundational):

# These can run in parallel:
Task T007: "Create Project dataclass"
Task T008: "Create Activity dataclass"
Task T009: "Create Relationship dataclass"
Task T010: "Create PaginationMetadata dataclass"

Phase 3 (US1 - Table Handlers):

# These can run in parallel:
Task T022: "Create PROJECT table handler"
Task T023: "Create TASK table handler"
Task T024: "Create TASKPRED table handler"
Task T025: "Create PROJWBS table handler"
Task T026: "Create CALENDAR table handler"

After US1 Complete (US2, US3, US4 can start in parallel):

# Developer A: User Story 2 (Activities)
# Developer B: User Story 3 (Relationships)
# Developer C: User Story 4 (Summary)

Implementation Strategy

MVP First (User Story 1 + 2)

  1. Complete Phase 1: Setup
  2. Complete Phase 2: Foundational
  3. Complete Phase 3: User Story 1 (Load XER)
  4. STOP and VALIDATE: Can load XER files successfully
  5. Complete Phase 4: User Story 2 (Activities)
  6. MVP COMPLETE: Can load XER and query activities

Incremental Delivery

  1. Setup + Foundational → Project ready
  2. User Story 1 → XER files load → Demo loading
  3. User Story 2 → Activities queryable → Demo activity queries
  4. User Story 3 → Relationships queryable → Demo dependency analysis
  5. User Story 4 → Summary available → Demo project overview
  6. Polish → Production ready

Parallel Team Strategy

With multiple developers after US1:

  • Developer A: User Story 2 (list_activities, get_activity)
  • Developer B: User Story 3 (relationships, predecessors, successors)
  • Developer C: User Story 4 (summary, milestones, critical_path)

Notes

  • [P] tasks = different files, no dependencies on incomplete tasks
  • [Story] label maps task to specific user story for traceability
  • Constitution mandates TDD: write tests first, verify they fail, then implement
  • Commit after each task or logical group
  • Stop at any checkpoint to validate story independently
  • All query tools must check for NO_FILE_LOADED condition