feat: add milestone_type field to distinguish start/finish milestones

Add milestone_type field to milestone queries that indicates whether
a milestone is a start milestone ('start') or finish milestone ('finish').

Changes:
- Add milestone_type column to activities table schema
- Parse milestone_type from XER TASK table (MS_Start/MS_Finish)
- Include milestone_type in list_milestones response
- Update contract tests for milestone_type field
- Update specs, contracts, and documentation

The milestone_type is determined by:
1. Explicit milestone_type field in XER (MS_Start -> 'start', MS_Finish -> 'finish')
2. Derived from task_type (TT_Mile -> 'start', TT_FinMile -> 'finish')
This commit is contained in:
2026-01-08 12:18:34 -05:00
parent bf2f85813e
commit a7b6b76db8
13 changed files with 345 additions and 198 deletions

7
.gitignore vendored
View File

@@ -38,9 +38,12 @@ htmlcov/
.tox/
.nox/
# XER files (may contain sensitive project data)
*.xer
# Schedule files
schedules/
# OS
.DS_Store
Thumbs.db
.claude/skills/